Stewart v. Newbury

220 N.Y. 379, 115 N.E. 984 (1917)

Quick Summary

Quick Summary Icon

Alexander Stewart (plaintiff), a contractor, entered into a contract with Newbury Manufacturing Company (defendant) to perform excavation and concrete work without a specified payment schedule. After Newbury refused to pay an interim bill submitted by Stewart, he stopped working and sued for non-payment and breach of contract.

The trial court supported Stewart’s claim for payment at reasonable intervals, but upon appeal, the Court of Appeals of New York reversed this decision, citing legal precedent that required substantial completion of work before payment is due when no payment schedule is agreed upon.

Facts of the Case

Facts of the case Icon

Alexander Stewart (plaintiff) is a contractor and builder from Tuxedo, New York. The defendants, partners in the pipe fitting business known as Newbury Manufacturing Company, engaged Stewart to perform excavation and concrete work for the construction of a concrete mill building at Monroe, New York.

The contract stipulated that Stewart would be paid on a per-cubic-foot and per-ton basis for his work, but there was no written agreement specifying when these payments were to be made. After starting work in July, Stewart continued until September 29th without receiving payment.

He then submitted a bill for the work completed, which Newbury (defendant) refused to pay, disputing the bill’s content and claiming the work was incomplete. Following this dispute, Stewart ceased work and filed a lawsuit against Newbury, alleging that Newbury had both refused to pay for the completed work and prevented him from fulfilling the rest of the contract.

Procedural History

History Icon
  1. Stewart filed a lawsuit against Newbury for non-payment and alleged interference with contract completion.
  2. The trial court found in favor of Stewart, instructing the jury that he was entitled to payment at reasonable intervals.
  3. Newbury appealed the decision to the Appellate Division, which affirmed the trial court’s ruling.
  4. Newbury then appealed to the Court of Appeals of New York.

I.R.A.C. Format

Issue

Issue Icon
  • Whether Stewart was entitled to payment at reasonable intervals during the construction project despite the absence of a payment schedule in the contract.
  • Whether his discontinuation of work due to non-payment was justified.

Rule of Law

Rule Icon

In the absence of an agreement regarding payment schedule in a contract for work, the party performing the work must substantially complete the agreed-upon tasks before demanding payment unless otherwise stipulated by custom or previous understanding between parties.

Reasoning and Analysis

Reasoning Icon

The Court of Appeals examined both parties’ arguments and testimonies regarding payment expectations and practices. Stewart argued that it was customary to receive 85% of payment monthly, while Newbury denied any such understanding or custom.

The trial court’s instruction to the jury suggested that absent an explicit agreement, Stewart was entitled to periodic payments during the project and could cease work if payments were not made.

However, the Court of Appeals disagreed with this interpretation of the law, referencing several precedents that establish an entire contract must be substantially performed before payment is due when no specific payment terms are included in the contract.

Consequently, since no agreement or custom regarding payment schedules was proven, the court held that Stewart was not entitled to interim payments and could not abandon the project on these grounds.

Conclusion

Conclusion Icon

The Court of Appeals reversed the previous judgment in favor of Stewart and ordered a new trial, with costs to be determined based on the outcome of this new trial.

Key Takeaways

Takeaway Icon
  1. An entire contract requires substantial performance before any payment is due if no specific terms for payment are included.
  2. Customary practices or understandings about payment schedules must be proven and agreed upon by both parties to enforce interim payments in the absence of explicit contractual terms.
  3. The Court of Appeals’ reversal emphasizes the importance of clear payment terms within contracts to avoid disputes over entitlement to payment.

Relevant FAQs of this case

What legal recourse does a party have when the other party fails to perform under a contract lacking explicit payment terms?

A party may seek a court determination to enforce payment based on the substantial performance of their obligations under the contract. The court typically requires that the work must be nearly complete or fulfill a large portion of the contractual obligation in such cases.

  • For example: A painter contracted to paint a house, who completes painting all but one minor area, could be considered to have substantially performed and might seek legal recourse for non-payment.

How does the absence of specified payment terms in a contract affect the interpretation of when payment is due?

The absence of specified payment terms usually leads the courts to expect that payment will be due upon substantial completion of the contract’s obligations, unless there is a proven customary practice or implied understanding between both parties dictating otherwise.

  • For example: A graphic designer who has delivered a complete draft of a commissioned artwork can claim payment upon this substantial completion, even if no specific milestones were set in the contract.

Under what conditions can customary business practices modify an otherwise silent contract regarding terms of payment?

Customary business practices can modify the understanding of a silent contract when there is reliable evidence that both parties had knowledge of such practices and agreed, implicitly or explicitly, to conduct their transaction in accordance with them.

  • For example: If it is an industry standard for suppliers to be paid within 30 days post-delivery, and both parties knew and operated under this presumption, the custom may effectively create a payment term within an otherwise silent contract.
Last updated

Was this case brief helpful?

More Case Briefs in Contracts