Drennan v. Star Paving Co.

51 Cal.2d 409 , 333 P.2d 757 (1958)

Quick Summary

Quick Summary Icon

Drennan (the plaintiff) was awarded a contract for a school construction project. Star Paving Company (the defendant) offered Drennan a quote of $7,131 for paving work, which was the lowest offer. Drennan accepted the offer, but Star later informed him that he miscalculated the cost and increased the quote to $15,000, which Drennan deemed insufficient. Drennan then had to search for a new subcontractor, incurring extra costs of $10,948. After completing the project, Drennan sued Star to recover these costs. The lower court awarded Drennan $3,817 for the difference between Star’s bid and the final paving cost plus fees.

The issue was whether Star was responsible for covering these extra costs.

The final ruling was that Star was responsible as the plaintiff had reasonable reliance on the original bid, and the bid was enforceable under the doctrine of detrimental reliance.

Rule of Law

Rule of Law Icon

Subsidiary guarantees shield both parties against financial loss if one party backs out of a bilateral contract offer. Instead of consideration, reasonable reliance binds the offeror.

Facts of the Case

Facts of the case Icon

Drennan (the Plaintiff) was preparing a proposal as a general contractor for a school construction project. As was standard, Drennan solicited bids for the necessary paving work from subcontractors. Star Paving Company (defendant) engaged Drennan and offered him a quote of $7,131 for the paving job. It was the lowest offer, and Drennan based his offer on Stars.

Drennan’s offer was the lowest; hence he was awarded the contract. However, Star informed Drennan that it had made an error in calculating its price and could only do the job for $15,000. Drennan deemed this insufficient and began searching for a new subcontractor to do the paving job. After months of searching, Drennan awarded a new subcontract to a business that bid $10,948 for the job, the lowest offer he could locate. Drennan filed a lawsuit against Star to recover financial losses sustained directly from Star’s decision to alter the bid price. The trial court awarded Drennan $3,817, the difference between Star’s bid and Drennan’s final paving cost plus fees. Star appealed.

Issue

Issue Icon

Should the defendant be responsible for covering any extra costs that Plaintiff paid?

Holding and Conclusion

Analysis Icon

Yes.

The court ruled in favor of the plaintiff and held the defendant liable for damages due to financial loss. The plaintiff relied on the defendant’s bid, which wasn’t modified, and the court found their reliance reasonable.

The defendant’s argument that the plaintiff failed to mitigate damages was dismissed as the plaintiff sought quotes from other subcontractors and selected the lowest bid.

Reasoning and Analysis

Reasoning Icon

The court reasoned that a general contractor cannot utilize a subcontractor’s bid as a contract, but it can be used through promissory estoppel. The doctrine of detrimental reliance requires the general contractor to have a sound reason for relying on a subcontractor’s bid.

The Plaintiff relied on the defendant’s bid, believing it to be unchangeable, therefore the defendant was responsible for carrying out the work at the original agreed upon price.

Relevant FAQs of this case

How do subsidiary guarantees protect both parties in a bilateral contract?

Subsidiary guarantees protect both parties in a bilateral contract by shielding them against financial loss if one party backs out of the contract offer. This protection is based on the principle of reasonable reliance, where the offer instead of consideration binds the offeror.

Subsidiary guarantees ensure that both parties are secure in their obligations and obligations, reducing the risk of financial loss and uncertainty in the event of a contract breach.

Can a general contractor use a subcontractor’s bid as a contract?

No, a general contractor cannot use a subcontractor’s bid as a contract. However, the bid can be used under the legal doctrine of promissory estoppel.

How does a court determine if a general contractor has minimized damages in a subcontractor dispute?

A court determines if a general contractor has minimized damages in a subcontractor dispute by evaluating the actions taken by the general contractor to mitigate the harm caused by the dispute.

This includes considering the steps taken to solicit quotes from other subcontractors and accepting the lowest offer to reduce the financial loss. The court also assesses whether the general contractor had a reasonable basis for relying on the original bid from the subcontractor in question.

References

Last updated

Was this case brief helpful?

More Case Briefs in Contracts